සි   |     |  

 Date: 2018-02-21   Answered 

2202/ 2018 - Question Asked By Hon. Mahindananda Aluthgamage, M.P.

    1. 2202/’17

      Hon. Mahindananda Aluthgamage,— To ask the Minister of Higher Education and Highways,—

      (a) Will he inform this House—

      (i) whether he is aware of the fact that the project to expand and carpet the Kandy, Gampola-Dolosbage road belonging to the Road Development Authority was implemented from 2013;

      (ii) whether he is aware of the fact that work was started from Kurunduwatta to Gampola as its first stage  and 8 kilometres were completed by the end of 2014;

      (iii) whether he admits that work of the remaining 4 kilometres from Gampola has stalled from January 2015; and

      (iv) whether steps will be taken to start work of the remaining 4 kilometres of this road as this is an essential road used by a large number of people?

      (b) If not, why?

       

Asked Date

2018-02-21

Asked by

Hon. Mahindananda Aluthgamage, M.P.

Ministry

Highways & Road Development

Legislature

Eighth Parliament of the D.S.R. of Sri Lanka

Session

1

Question History

Answer

Developing the remaining portion of Gampola- Dolosbage Road

Answered Date

0000-00-00





Copyright © The Parliament of Sri Lanka.