 Date: 2017-07-27   Answered 

1603/ 2017 - Question Asked By Hon. (Prof.) Ashu Marasinghe, M.P.

    1. 1603/’17

      Hon. (Prof.) Ashu Marasinghe – To ask the Minister of Power and Renewable Energy,—

      (a) Will he  inform this House—

      (i) whether he is aware that a  main underground power supply line which provides electricity to the city of Colombo has been inactive  for about 3 years ;

      (ii) the  electricity capacity of the aforesaid supply line;

      (iii) the reason for the delay in taking steps to restore the aforesaid supply line;

      (iv) the officers who are  responsible  for the  delay in repairing the aforesaid supply line;

      (v) the disciplinary action that have been  taken by the Ministry or Ceylon Electricity Board against each of the aforesaid officers  by now, separately; and

      (vi) whether action will be taken to modernize the national grid  in order to ensure a continuous supply of electricity in  the city of Colombo ?

      (b) If not, why ?

       

Asked Date

2017-07-27

Asked by

Hon. (Prof.) Ashu Marasinghe, M.P.

Ministry

Power and Renewable Energy

Legislature

Eighth Parliament of the D.S.R. of Sri Lanka

Session

1

Question History

Answer

Underground Power Supply Line to Colombo - Inactive

Answered Date

0000-00-00





Copyright © The Parliament of Sri Lanka.

All Rights Reserved.

Design & Developed by  TekGeeks